Start:
Saturday, June 11, 2016 - 5:00am
End:
Saturday, June 11, 2016 - 8:00am
Description
On Saturday, June 11, 2016 between 5:00 AM and 8:00 AM, ITS will:
Upgrade the two primary NetApp clusters
Which data center - ITF and the Lindquist Center Facility (LC14)
Expected impact on services - each volume will experience two brief pauses in IO (10 to 30 seconds each)
Expected duration - total cluster upgrade time is three hours
Please do not schedule major IT work on Saturday, June 11, 2016 between the hours of 5:00 AM and 8:00 AM.
Last updated:
Saturday, June 11, 2016 - 8:01am