Start:
Saturday, March 11, 2017 - 12:00am
End:
Saturday, March 11, 2017 - 9:00am
Description
Scheduled work from midnight to 6:00AM: Apply changes to router control-plane policing and upgrade switch software
Data center(s): Information Technology Facility (ITF) and Lindquist Center (LC)
Expected impact on services: None
Contact Person: Jay Ford
Scheduled work from 6:00AM to 9:00AM: upgrade NetApp clusters
Data center(s): Information Technology Facility (ITF) and Lindquist Center (LC)
Expected impact on services: Each volume will experience two brief pauses in IO for 10 - 30 seconds each
Contact person: Mark Weber
Last updated:
Saturday, March 11, 2017 - 9:00am